The Building Safety Act 2022 (BSA) introduced transformative regulations to enhance safety in high-risk buildings (HRBs), primarily residential developments over 18 metres tall. Key among these are the Gateway 2 and Gateway 3 checkpoints, designed to ensure robust oversight at critical stages of construction. However, these procedures have inadvertently created delays, further straining the housing crisis in the UK.
According to the Fire Industry Association (FIA), only 6% of new building applications meet the statutory 12-week approval timeline. These delays discourage high-rise construction, especially in urban areas where such developments are essential for addressing housing shortages. This article explores the challenges posed by the Gateway process and examines the FIA’s recommendations for improvement.
Understanding Gateway 2 and Gateway 3
The Gateway checkpoints were introduced to enforce stricter safety regulations for HRBs.
– Gateway 2: Requires approval of design plans before construction begins. This ensures that safety measures are embedded from the start.
– Gateway 3: Provides final clearance upon project completion, confirming that the completed building meets all regulatory requirements.
While these measures are critical for ensuring safety, their implementation has faced significant challenges, particularly at Gateway 2.
Read Also : Everything You Need to Know About Gateway 3 and Building Safety Act
Read Also : Why the Golden Thread is Crucial for Construction Safety: Learning from Grenfell
Challenges in Gaining Gateway 2 Approval
Ìý1. Lack of Clarity in Submission Requirements
Developers and designers report that submission requirements for Gateway 2 are ambiguous. This often results in the submission of excessive documentation during early project stages, which complicates the review process. The lack of clear guidance wastes resources and delays approvals.
Ìý2. Absence of Pre-Submission Consultations
The current process does not allow for pre-submission consultations with the Building Safety Regulator (BSR). This prevents developers and designers from resolving potential issues before formal submission. Consequently, applications are rejected for technical reasons, forcing costly and time-consuming revisions.
Ìý3. Limited Communication with Registered Building Inspectors (RBI)
Restrictions on direct communication with RBIs during reviews exacerbate delays. Without the ability to discuss technical disagreements in real time, designers face prolonged resolution timelines, further stalling project progress.
Ìý4. Impact of Major Changes During Construction
Design changes during construction, categorised as Major Changes, require additional BSR approval to avoid legal penalties. This process adds another layer of complexity, increasing the risk of project delays and escalating costs.

Implications for Construction and Housing
Ìý1. Delays in Urban Housing Projects
The stringent approval processes have disproportionately affected high-rise developments in urban areas, where they are most needed. Many developers opt to reduce project sizes to bypass Gateway 2 requirements, limiting the availability of housing in densely populated regions.
Ìý2. Risk of Unoccupied Buildings
Delays at Gateway 3 mean completed buildings cannot be occupied until final clearance is granted. This leaves newly built properties sitting empty for months, further compounding housing shortages and creating financial strain for developers.
Ìý3. Reduced Confidence in High-Rise Projects
The procedural inefficiencies discourage investment in HRBs, as developers perceive these projects as high-risk and resource-intensive. This undermines efforts to meet housing demand, particularly in cities where vertical expansion is critical.
FIA Recommendations for Process Improvements
To address these challenges, the FIA has proposed several measures to streamline the Gateway process while maintaining safety standards:
Ìý1. Phased Submissions
Phased submissions would allow developers to gain initial approvals for general arrangements and high-level documents early in the process. Detailed designs could then be submitted in later phases, reducing the burden of excessive documentation during the initial review.
Ìý2. Clearer Documentation Guidelines
Providing clearer guidance on the required documentation for Gateway 2 would help developers prepare more targeted and complete applications. This would minimise rejections and reduce wasted resources.
Ìý3. Enhanced Communication Channels
Allowing direct communication between developers, designers, and RBIs during reviews would expedite the resolution of technical disagreements. This collaborative approach would ensure that issues are addressed efficiently, reducing delays.
Ìý4. Increased Capacity at the BSR
The FIA and other stakeholders have called for greater investment in the BSR to expand its capacity. By hiring and training more inspectors, the regulator can handle the growing volume of applications more effectively.

Balancing Safety and Efficiency
The intent of the Building Safety Act is clear: to prioritise the safety and well-being of residents in high-risk buildings. However, the current implementation of Gateway 2 and Gateway 3 processes highlights the need for a balance between safety and efficiency. The delays caused by these procedures are hindering progress in addressing the UK’s housing crisis.
As the FIA emphasised, procedural inefficiencies must be addressed without compromising safety standards. By adopting phased submissions, improving communication, and clarifying guidelines, the construction industry can work towards a streamlined Gateway process that supports both safety and housing development goals.
The delays caused by the Building Safety Act’s Gateway processes are a significant barrier to high-rise residential construction. While these checkpoints are essential for ensuring safety in HRBs, their current implementation has created challenges that cannot be ignored.
By addressing these issues, the construction sector can align with the BSA’s safety objectives while reducing delays and inefficiencies. As the FIA stated, maintaining high standards of competency and quality control is non-negotiable, but procedural improvements are critical for supporting the government’s housing targets and fostering confidence in high-rise projects.
The road ahead requires collaboration between regulators, developers, and industry stakeholders to refine the Gateway process and ensure that building safety and housing development move forward together.
Read Also : New vs. Old Buildings: How the Golden Thread Can Restore Confidence in Modern Construction
Read Also : Understanding Gateway 3 and the Golden Thread: The Blueprint for Safer Buildings